W J Drennan Ltd t/a High Hedley Biogas Plant receive their environmental permit

The Environment Agency has today issued Permit EPR/LB3536AZ/A001 which will allow operations to commence as soon as the construction phase moves on to commissioning of the plant. We will start seeding the Digesters with a blend of Digestate and Dairy Cattle Slurry during October in preparation for our first Food […]

Build progress – The detail

The Digesters have finished curing and the tensioning cables will be tightened and completed next week prior to the water pressure tests to confirm there are no leaks. Once this is complete the internal Digester stainless steel heating system will be installed along with the mixing technology. The Digester feeding […]

Build progress – NPG electrical substations foundations complete, bund wall progressing

The concrete base slab for our Northern Power Grid Substation has now been poured and the bund wall is progressing nicely down the Lagoon side of the Biogas Plant site. Ground preparation for the 2 x 23m diameter Anaerobic Digester tanks also now in progress.

Our Newsletter

Enter your details below to be kept up to date of project developments.

Latest from Twitter