Build progress – The detail

Categories: Anaerobic Digestion, Progress, W J Drennan  /   Posted on: July 31, 2014 5:07 pm

The Digesters have finished curing and the tensioning cables will be tightened and completed next week prior to the water pressure tests to confirm there are no leaks. Once this is complete the internal Digester stainless steel heating system will be installed along with the mixing technology. The Digester feeding pit has been completed in the mixing room floor area of the Reception Building and the Pasteurisation, Mixing and Control rooms are being formed. The east wall of the Reception Building is now complete which provides an idea of the building final appearance.